Citrus County Central Landfill Phase III
Aerial photos of the Citrus Country Central Landfill Phase III Project
as of November 9, 2010.
-->
Aerial photos of the Citrus Country Central Landfill Phase III Project
as of November 9, 2010.
The Citrus County Central Landfill Phase III Expansion project began for COMANCO in July, and since then our teams have completed construction of the access road, sub-base limerock installation, water retention pond construction, earth cutting & filling of cell, trenching and construction of a stormwater ditch on east end of the cell. We’re in process of installing 8” solid HDPE pipe, GSE Bi-Planar and Nonwoven geotextile and Mirafi Biaxial Geogrid. Over the next few days liner deployment on the slopes will continue, followed by tie-in of the floor panels.