Citrus County Central LF Phase 3 Expansion
The Citrus County Central Landfill Phase III Expansion project began for COMANCO in July, and since then our teams have completed construction of the access road, sub-base limerock installation, water retention pond construction, earth cutting & filling of cell, trenching and construction of a stormwater ditch on east end of the cell. We’re in process of installing 8” solid HDPE pipe, GSE Bi-Planar and Nonwoven geotextile and Mirafi Biaxial Geogrid. Over the next few days liner deployment on the slopes will continue, followed by tie-in of the floor panels.