COMANCO Click for detailed COMANCO contact information, maps, directions and more


Palm Beach NCRRF Cells 7-10 Partial Closure

The Palm Beach NCRRF Closure is over halfway completed with sod being installed on the West Slope and liner being finished on the East Slope earlier this month. Troy Watral is the Project Manager on this job from the Environmental Construction Services Division, and he is teamed up with Earthwork Superintendent Ivan Fogarty, Liner Superintendent Jorge Barrantes, and Project Engineer Nick Bridges. CDM is the General Contractor, & SWA is the Owner.

Posted by nickbridges 

Comments [0]


WSI/SLD C&D Landfill -- Aerial view of sod progress as of 4/20/10

Sld_landfill_01_4-20-10

Sodding is in progress, and project is scheduled to complete on-time in May.