COMANCO Click for detailed COMANCO contact information, maps, directions and more


Citrus County Central Landfill Phase III

Aerial photos of the Citrus Country Central Landfill Phase III Project
as of November 9, 2010.

Filed under  //   citrus county   construction   fl   florida   geogrid   geosynthetic   landfill   solid waste  
Posted by email 

Comments [0]


Evergreen LF - Concrete Truck Pad

Installation of reinforcing bars for a concrete truck pad at Veolia ES’s Evergreen Landfill in Valdosta GA.

Filed under  //   :landfill   georgia   leachate   reinforcement   solid waste   sump   veolia   waste handling  
Posted by email 

Comments [0]


Citrus County Central LF Phase 3 Expansion

The Citrus County Central Landfill Phase III Expansion project began for COMANCO in July, and since then our teams have completed construction of the access road, sub-base limerock installation, water retention pond construction, earth cutting & filling of cell, trenching and construction of a stormwater ditch on east end of the cell. We’re in process of installing 8” solid HDPE pipe, GSE Bi-Planar and Nonwoven geotextile and Mirafi Biaxial Geogrid. Over the next few days liner deployment on the slopes will continue, followed by tie-in of the floor panels.

Posted by email 

Comments [1]


Update on WLSSD landfill cap project

We are progressing at the WLSSD "Western Lake Superior Sanitary District" 80 Acre Landfill Closure. Duluth MN. as a sub contractor for General Contractor Ames Construction Inc. out of Burnsville, MN.   Project Manager Clayton Lung, Supt.  Tony Sanchez.    

Posted by email 

Comments [0]


DeSoto County Landfill - Coming to the end!

Most recent pictures of the Desoto County Landfill Zone 2 & Partial Zone 3 Closure. The project should be wrapping up in early May.

 

 

Posted by nickbridges 

Comments [0]